Final Line Inspection Pit -TOYOTA
Market: ICI
Year: 2012
Owner: Toyota
Consultant: Toyota
Location(s): Cambridge, ON
Contract Type: Fixed
Contract Value: $1,200,000
Project Duration: 1 week
Project Status: Complete
Project Description: Toyota Christmas holiday shutdown job performed on an existing slab area in the plant transformed into a final line inspection pit.
Project Scope:
Installation of hoarding system from floor slab to roof
Sawcut and demo concrete floor slab
Excavation and backfill
Form and pour new foundation and slab
Finish, coat and seal new slab