Trans Canada Corporation

Market: Oil & Gas

Year: 2008

Owner: Trans Canada Corporation

Consultant: SNC Lavalin

Location(s): Richardson, Kendal, Grenfell & Moosomin SK

Contract Type: Cost Reimbursable/Target Price

Contract Value: $21,750,000

Project Duration: 18 Months

Project Status: Complete

Project Description: Originating at Hardisty, AB, the Canadian portion of the Keystone Project involved the conversion of approximately 864km of existing mainline pipeline facilities for natural gas to crude oil transmission service and 373km of new pipeline, in addition to sixteen (16) pumping stations being required.

Raven Construction Management Inc. was responsible for civil work pertaining to four (4) pumping stations located east of Regina, SK to the Manitoba border.

Project Scope:

  • Site preparation and grading activities

  • Excavation and backfill

  • Steel driven pile installation

  • Concrete foundations for pumps, process equipment, electrical equipment and supports

Highlights: Due to the target price nature of our contract, which provided both positive and negative incentives, the consistent tracking of changes was extremely important. By project completion, total contract value including change orders had increased by 300%.