HORNER TS- HYDRO ONE- STATE GROUP
Market: Power Generation / Distribution
Year: 2020
Owner: Hydro One
Consultant: FNX
Client: State Group
Location(s): Etobicoke, ON
Contract Type: Fixed
Contract Value: $1,800,00.00
Project Duration: 10 Months
Project Status: Complete
Project Description: Project located in Etobicoke, ON, involved the construction of a new MV GIS Building for Hydro One at their Horner Transformer Station
Scope: Raven Construction was responsible for all civil activities associated with the construction of the new building. Our scope included:
Excavation and backfill operations
Yard drainage and grading
Formwork, rebar and cast-in-past concrete for building foundation and slab on grade
Foundation waterproofing
Form and pour suspended slab
Install built up roof parapet
Pour roof topping
Supply and install all doors and hardware
Supply and install suspended ceilings and bathroom finishes
Highlights: New building was located at the low point on the site and water was a constant issue, RAven Construction managed to control the water with the use of 2 large sumps on the East side of the building, maintaining the water level below the new foundations.
All material had to be delivered on an as needed basis, there was no extra room on site for material storage.