Rothsay- Maple Leaf Foods-AMEC Geomatrix
Market: Environmental
Year: 2005
Owner: Rothsay
Consultant: McCavour Engineering
Client: AMEC Geomatrix
Location(s): Dundas, ON
Contract Type: Design Build/Fixed Price/Cost Reimbursable
Contract Value: $4,000,000
Project Duration: 12 Months
Project Status: Complete
Engineered and constructed in 2 phases over 2 years, construction activities at Rothsay's Waste Water Treatment Plant located at their meat rendering facility in Dundas, ON were successfully completed by Raven Construction in September of 2005 in support of Rothsay meeting its environmental commitments to both the Provincial Government and local community.
Raven Construction was responsible for the design and construction of all civil, structural and architectural components of the project, including the following:
Aeration Basin
Clarifier
IWMS Building and Pre-Treatment Building
Site preparation and grading activities
Excavation and backfill
Steel driven pile installation
Cast-in-place concrete installation
Fabrication and installation of HDPE underground piping
Highlights: Raven Construction's largest contract award since company inception in 2003.
Collaborative effort by all facets of the Project (Owner, Consultants, Raven etc.) resulted in the Project being successfully completed on time and under budget, with zero recordable safety incidents and quality non-conformances.